Get Instant Help From 5000+ Experts For
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing:Proofread your work by experts and improve grade at Lowest cost

And Improve Your Grades
myassignmenthelp.com
loader
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Guaranteed Higher Grade!
Free Quote
wave

Analyzing construction costs, design considerations, load calculations, and structural design

The project covers the process of construction from the moment the idea is conceived till it is ready for hand over. It describes in detail the process of construction by analysing the construction costs, the design considerations, load calculation and structural design, bar selection and designing for shears. The foundation will also be designed to the AS3600 and from here the write-up of the project sections, primarily question 2 and 3 explaining the various terms and design components associated with the project.

The design documentation in this case includes the:

Loading (dead and live) refer to AS1170

The designing of structural steel is in adherence to AS4100

The geotechnical engineer has recommended the use screw piles when designing for safe bearing capacity.

The design of concrete members is done according to AS3600

For steel encasement, mix shall be 1:2:4

21 day cure

As per the engineer’s recommendation, all bars are to be lapped. Bar sizes to be used include: N12, N16, N20 and N24

Erection And Fabrication of steel members done according to AS1554 and AS4100

The surface of steelwork is done according to AS1627

All steelwork that is not enclosed is to be painted.

Internal protective coating is to be done according to AS1627. The minimum 35um primer to be used is zinc phosphate.

External protective coating is to be done according to AS1627. This includes the application of two layers of i.e. alkyd primer and a coat of not more than 50um.

Mega and super-structures have been engineered with cutting-edge methods to provide building stability, comfy, sustainable, and renewable applications for a desirable life cycle. A wide range of the construction methods that were in use in earlier generations or eras have been incorporated in the current trends with changes to increase the structural durability. Portal steel frame systems have been used during construction since the mid-1900s. The approach assures overall performance in regards to expenses, time saving, making sure the integrity of the structure. But, the method of construction is gaining root in the present day construction sector thanks to the capability to withstand as considerable wind loading affecting the form and stability deal as wind movement end result and deliver stability of the shape. The elements specializes in assisting with the structural resistance at the side of the vertical stability of the building when used along with portal frames.

The construction of the steel members follows a few standard ways wherein each they are incorporated at the bottom slab of the event or a casting pad created for a specific phase of the event. Once the initial concrete has been placed into the long, member, stability in the slabs is ensured by incorporating steel columns, beams and braces. When this is done, connections can be commenced from the column to the beams to the trusses and finally the roof. To set them up in place, they can be carried by use light plant machines, humans but in complex cases crane is used to move the steel sections to the site, after which they connect with the other steel sections within the construction site (Kurrer, 2008).

Designing of foundations and adherence to regulatory codes and standards

The steel sections’ ability to resist lateral effect of the wind load is contributed to further which is probably added within the path of the preliminary degrees of building them. Steel rebars can be introduced to the frame systems to improve the structure of the steel sectionss. It is generally implied that a well-preferred to use I or H sections for these frames though angle lines can be used as bracing depending on the dimensions. What’s more is, there are factors or elements of interest for the crewmembers working in an environment with steel frames that include environmental, which has wind in order to build the crane risky and consequently the steel section to fall on the personnel should be noted. Once the section is well bolted and welded, it can be considered sturdy enough to provide the effective resistance to wind forces (Pessiki and Mlynarczyk, 2003).

Connecting of the members of the steel sectionss in is done with the use of the method of a close fit joint during which one steel sections is above the next in the link to make a guided joint for each steel sections. Additionally, joint filling materials location unit used, which might be go with hobby in their thermal moves, climate resistance, and consequently the structural actions of the constructing once of completion. Therefore, as the wind blows along the course of one steel sections, the rest of the steel sections facilitate the support of the member especially as they may be all interconnected, they remain powerfully established to form a rigid network of support and bracing.

Some of the notable benefits of incorporating steel sections during the construction process is that the increased rigidity of the structure. The design and production process of the steel sections is done with the focus of producing steel sections of a particular predetermined weight. The in this case are designed to be independent systems which offer helpful and rigid bracing support for the whole system of the building, for this reason they are designed with the steel sections having a double bracing or welded plate to provide a firmer bracing effect and preserve its stability. Once the steel sections are ready collectively, extra reinforcement of the steel sections is required to be meshed with them which is then completed (Yu, 2000).

The use of portal frames with connecting edges of the steel sections is currently a method that a many cutting-edge companies have adopted. The device of creating the steel sections is discussed above, and each one of the technical areas pre-described are incorporated to create precision and exactness of the steel sections (Lam et al., 2013).

In the documentation, there is no geotechnical report or architectural drawing so any discussions made can only be made in relation to the structural engineering documentation. However the technology at the moment allows for the designers and contractors to be able to save some time beforehand and especially in the case of this building, particular attention is given to giving it freely. 

Erection and fabrication of structural steel and its various benefits

The problems experienced during the acquisition of the documentation of these civil engineering projects:

These are:

The unavailability of public records in the public council sectors.

Some of the geotechnical tests conducted in the design and construction have been very tedious making the obtaining documentation very challenging.

Site visits are a mandatory construction procedure as they mainly involve going to check out the work done by a contractor and provide the approvals if need be for the continuation of the job. Site visits happen either regularly after a predefined interval of time or after the completion of a predetermined stage of the construction. They comprise members of every party including the client’s, consultant and contractor’s team who are the project stakeholders (Toole, 2002).

Periodic meetings at the building site are an essential a part of the target meeting objectives of the entire project. If held regularly, the site meetings happening among the project leads especially when dealing with an issue can aid in facilitating better information sharing and the joint effort almost always guarantees that the challenge will be solved or a way around it will be charted. This leads to the goals being completed efficiently. Challenge in the site can be attributed to poor management with the key aspect being a lack of proper communication and information management.

As such, it is important to hold the meetings normally and scheduled prior, perhaps on a weekly or monthly basis, a decision relying on the agendas to be discussed, although at the end of the day, the scale and complexity of the construction project may prove to require non-standard site meeting schedule. As such, their purpose will be reporting developments, permitting dialogue when of any problems or troubles arise, and allowing the proposal of solutions or alternatives. They provide an opportune possibility for bi-lateral discussions of any issues which have arisen or which are expected (Mustapha and Naoum, 1999).

For this construction, the latest site visit was conducted on the 10th of October 2017. This was a monthly meeting meant to periodically check on the progress and discuss about any issues on the construction site. The meeting conducted prior to this was held 2 weeks before and was not part of the regular monthly meeting but rather was held to approve the work done on the completion of the third phase of the steel truss assembly. So far, 7 meetings have been held, both monthly and at the end of every phase.

An amalgamation of the reports of all site visits indicate the few agendas have included administrative changes, end phase approval, cost analysis, stock taking of machinery and tools, quantity measurements and issuing of payment certificates. So far, defects observed have been either rectified or ignores. The specifications have also been modified over these site meetings. Over the last site meeting, photographs were taken to compliment the written reports so as to enable further discussion and deliberation. In this meeting, matters to be discussed included:

The steel beam member on the western section of the structure that has been affected by the torsional turning moment due to wind loading giving it a slight twist. The turn is not clearly visible from afar and one would need to observe closely. It was agreed that it would not have any effect on the integrity of the structure and could therefore be left as is.

Challenges in acquiring documentation for civil engineering projects

The additional bolts connecting the steel column section to the trusses over the welded plate and brace. This was agreed on as the wind loading on the site had surpassed the expected wind loading values.

Alteration of the specifications to allow for a sturdier roofing system. While part of the roof had been constructed, it was agreed on that the specifications are to be revised to provide for a an extra set of truss members to help counter the unexpected wind loading.

In the photos taken, most structural members are as described with the exception of a few which have been modified to adapt to conditions on the site. The steel rafter connections are modified to contain an extra two bolts each because of the excessive and unexpected wind load which was only noticed after the design. 

In trying to keep the members as close to the design as possible, the rest of the components have been left as is.

Wall steel sectionss have also been modified a bit to include an extra layer of steel bracing on the Western side as that is the most affected side of the building. Their bracings have, however remained in alignment with each other in an effort to minimize any adverse design differences.  

Every other component is as is on the drawings and specifications. As much as the construction is still yet to be done, it can be concluded that further differences will be few on the ground.

Apart from the modifications, there are slight variations on the western most ceiling beam. Unlike the modifications, these are not welcome changes and need to be avoided as much as possible. The western most ceiling beam has undergone a torsional effect as it is slightly rotated on one end which cannot be fixed. In that case, it would go on as is but only after the involvement the project engineer in the decision making. 

References:

AustralianStandards.com.au: The Leading Australian Standard Site on the Net. 2013. AustralianStandards.com.au: The Leading Australian Standard Site on the Net. [ONLINE] Available at: https://www.australianstandards.com.au/. [Accessed 10 October 2014]

Barrie, D.S. and Paulson, B.C., 1992. Professional construction management: including CM, design-construct, and general contracting. McGraw-Hill Science/Engineering/Math.

Construction work code of practice, 2012, Viewed October 10 2014, <https://www.safeworkaustralia.gov.au/sites/swa/model-whs-laws/model-COP/Documents/Historical%20model%20Codes%20of%20Practice/Construction-Work-V1.doc>.

Chau, K.W. and Anson, M., 2002. A knowledge-based system for construction site level facilities layout. Developments in Applied Artificial Intelligence, pp.25-67.

Chen, Z., Ge, H., Kasai, A. and Usami, T., 2007. Simplified seismic design approach for steel portal frame piers with hysteretic dampers. Earthquake engineering & structural dynamics, 36(4), pp.541-562.

Da Silva, J.G.S., De Lima, L.R.O., Vellasco, P.D.S., De Andrade, S. and De Castro, R.A., 2008. Nonlinear dynamic analysis of steel portal frames with semi-rigid connections. Engineering Structures, 30(9), pp.2566-2579.

Degertekin, S.O., 2008. Optimum design of steel frames using harmony search algorithm. Structural and multidisciplinary optimization, 36(4), pp.393-401.

Josephson, P.E. and Hammarlund, Y., 1999. The causes and costs of defects in construction: A study of seven building projects. Automation in construction, 8(6), pp.681-687.

Kurrer, K.E., 2008. The history of the theory of structures: from arch analysis to computational mechanics. International Journal of Space Structures, 23(3), pp.193-197.

Lam, D., Ang, T.C. and Chiew, S.P., 2013. Structural steelwork: design to limit state theory. Crc Press.

Liu, M., Burns, S.A. and Wen, Y.K., 2005. Multiobjective optimization for performance?based seismic design of steel moment frame structures. Earthquake Engineering & Structural Dynamics, 34(3), pp.289-306.

Mahfouz, S.Y., 1999. Design optimization of structural steelwork (Vol. 318). University of Bradford.

Mustapha, F.H. and Naoum, S., 1998. Factors influencing the effectiveness of construction site managers. International Journal of Project Management, 16(1), pp.1-8.

Nethercot, D., 2001. Limit states design of structural steelwork. CRC Press.

Pessiki, S. and Mlynarczyk, A., 2003. Experimental evaluation of the composite behavior of precast concrete sandwich wall steel sectionss. PCI journal, 48(2), pp.54-71.

Toole, T.M., 2002. Construction site safety roles. Journal of Construction Engineering and Management, 128(3), pp.203-210.

Wrzesien, A., Lim, J.B. and Nethercot, D.A., 2012. Optimum joint detail for a general cold-formed steel portal frame. Advances in Structural Engineering, 15(9), pp.1623-1639.

Yu, W.W., 2000. Cold-formed steel design. John Wiley & Sons.

Cite This Work

To export a reference to this article please select a referencing stye below:

My Assignment Help. (2022). Construction Process And Design Considerations: Structural Steel, Foundations, And Documentation. Retrieved from https://myassignmenthelp.com/free-samples/200470-construction-technology/erection-and-fabrication-file-A9D6A2.html.

"Construction Process And Design Considerations: Structural Steel, Foundations, And Documentation." My Assignment Help, 2022, https://myassignmenthelp.com/free-samples/200470-construction-technology/erection-and-fabrication-file-A9D6A2.html.

My Assignment Help (2022) Construction Process And Design Considerations: Structural Steel, Foundations, And Documentation [Online]. Available from: https://myassignmenthelp.com/free-samples/200470-construction-technology/erection-and-fabrication-file-A9D6A2.html
[Accessed 19 August 2024].

My Assignment Help. 'Construction Process And Design Considerations: Structural Steel, Foundations, And Documentation' (My Assignment Help, 2022) <https://myassignmenthelp.com/free-samples/200470-construction-technology/erection-and-fabrication-file-A9D6A2.html> accessed 19 August 2024.

My Assignment Help. Construction Process And Design Considerations: Structural Steel, Foundations, And Documentation [Internet]. My Assignment Help. 2022 [cited 19 August 2024]. Available from: https://myassignmenthelp.com/free-samples/200470-construction-technology/erection-and-fabrication-file-A9D6A2.html.

Get instant help from 5000+ experts for
question

Writing: Get your essay and assignment written from scratch by PhD expert

Rewriting: Paraphrase or rewrite your friend's essay with similar meaning at reduced cost

Editing: Proofread your work by experts and improve grade at Lowest cost

loader
250 words
Phone no. Missing!

Enter phone no. to receive critical updates and urgent messages !

Attach file

Error goes here

Files Missing!

Please upload all relevant files for quick & complete assistance.

Plagiarism checker
Verify originality of an essay
essay
Generate unique essays in a jiffy
Plagiarism checker
Cite sources with ease
support
Whatsapp
callback
sales
sales chat
Whatsapp
callback
sales chat
close